Drywall started going up today. When I stopped by, they were done with the top floor and most of the main floor. I assume that they’ll finish the basement tomorrow. So far its looking pretty good, as soon as the guys are done hanging it, someone will come in and taping, mud, texture. Our contractor expects the process to take about two weeks.

Siding