Preparing for the Foundation

Sewer work finished up on Friday, the last of the equipment was removed this morning.  We have a schedule for progressing, on Monday the 3rd, our excavator is scheduled to come and dig out a hole for our basement, then the foundation guys will come in on Wednesday.  Before then, we are getting a surveyor to come out to locate the foundation…  Aside from that, there’s not a whole lot happening this week.