Budget

  • $5,000 – Excavation
  • $12,000 – Sewer and utilities
  • $16,000 – Foundation and slab
  • $15,000 – SIP fabrication
  • $7,000 – Framing materials
  • $11,200 – Framing labor and SIP installation
  • $20,000 – Windows and doors
  • $3,900 – Rough Plumbing
  • $6,700 – Rough Electrical
  • $7,000 – Ecoroofs
  • $14,700 – Siding
  • $2,000 – Additional insulation
  • $3,300 – Drywall
  • $11,400 – Cabinets. countertop, built-ins
  • $6,500 – Flooring
  • $6,500 – Appliances
  • $3,000 – Finish plumbing and fixtures
  • $1,500 – Finish electrical and fixtures
  • $2,500 – Deck
  • $4,000 – Misc. finish
  • $6,000 – Misc. stuff
  • $8,000 – Permits

Total Soft Costs – $173,200

  • $18,500 – Contractor Fees
  • $1,000 – Engineering

Total Budget – $192,700

  • $12,000 – System Development Charges (Waived)
  • $20,000 – Architectural fees for design and project/construction management (Donated by owner)

Total Expected Project Value –  $224,700