August 17th, 2009

Plumbing
Today was a busy day of getting things done. Our plumber showed up today to rough in sewer and water for the house, this actually all happened really quickly in just an afternoon. In addition to that, foundation drains went in. Read the rest of this entry »
foundation · LEED · merkled · plumbing · sewer · windows
Posted in Site Photos, updates by Matt · No Comments »
August 8th, 2009

Concrete Pour
Its been an exciting few days to catch up on. On Friday very early concrete was poured.
Read the rest of this entry »
foundation · photos · sewer
Posted in Site Photos, updates by Matt · 1 Comment »
August 1st, 2009

Yesterday our surveyor made it out to locate the house on our lot. It was a slow week in general, which was probably good that a lull in the schedule coincided with a week of excessive heat. But on Friday our surveyor staked out the corners of the house so that on Monday when the excavator comes in, he’ll know where to dig, and when the foundation guys come on Wednesday, they’ll be set as well. Read the rest of this entry »
excavation · foundation · Oak Basin Sewer Project · photos · sewer · survey
Posted in Site Photos, updates by Matt · No Comments »
July 23rd, 2009

How I found our street this morning
Read the rest of this entry »
photos · sewer
Posted in Site Photos, updates by Matt · No Comments »